home about us lump sum fees seminars news contact
our services
matters

Defect rectification
Contract drafting & review
Security of payments act
Insurance & collapses
Energy
Railways
Airports
Ports
Defence
Legislation/govt.

Our clients
Our Staff
brett vincent
We Take Ownership

When we take on a matter, we take complete ownership of it, we provide clear, direct advice and we are not afraid to make decisions and give you clarity at every step of the way. Our matters are run in the way you would run any project – we create programs, we set budgets and we stick to it.

We have people who undertake front end and back end work.

The following matters have been undertaken by people who work with use at Vincent CCL or by Brett Vincent personally.

Defect Rectification

Houses and Units
A Mum and Dad developer in the suburbs created a dual occupancy. The builder’s work was defective in the extreme. The case went to the Department of Fair Trading with a number of experts. The case was successfully resolved to the satisfaction of our clients.

In another matter, a substantial builder with 30 years experience has had claims made against it in respect of defects by an insurer and unit holders of a strata plan. The defects are over 10 years old. In this case the catalog of defects was poorly documented by the other side’s solicitors. We were able to respond to the evidence, saving our client from corrective work that could not have been its to rectify. Importantly we used a team of experts and barristers who specialise in construction work and, in particular, defects.

International Arbitration in Hong Kong for Defective Work to the Tsing Ma Bridge.
The defect rectification of certain substantial parts of the works on the Tsing Ma Bridge in Hong Kong resulted in an international arbitration spanning 4 countries and involved a substantial claim. Extraordinarily large pieces of the Tsing Ma Bridge were manufactured on an assembly line in China and floated downriver and lifted into place in Hong Kong. Brett Vincent defended the Hong Kong sub-contracting company over a period of three years, which resulted in the London arbitration being settled before any substantial hearing.

30 Storey Building Demolition because of Fraud
The collapse and subsidence of a recently constructed thirty storey building in Hong Kong resulted in litigation and prison sentences for certain key engineers on site. The engineer had fraudulently certified that the piles had hit bedrock at 60 metres, when in fact the piles had only been dug to less than fifteen metres. The engineer’s mistake was that he put all the short piles in one corner. Had the engineer spread the piles out around the building, the fraud would never have been detected. The fraud caused a serious loss of confidence in public housing in Hong Kong. Litigation against the building company was commenced in order to recover the demolition costs of the building and other losses. For political reasons of public confidence the matter went to a hearing.

Brett Vincent, along with other Hong Kong legal personnel, prepared evidence to successfully recover damages from the contractor.

Geotechnical Defects
A geotechnical engineering company provided advice that resulted in the collapse of the flexible pavement at a port waterfront on reclaimed land. The designed flexible pavement was recommended for earthworks on which heavy containers and moving equipment would be loaded and transported. The pavement ultimately failed. The geotechnical conditions of the soil proved to be inadequate to carry the loads upon which the containers traveled. The tensely fought case against the geotechnical engineer settled after the plaintiff’s evidence of damages were successfully cross-examined by counsel for our client.

Corroding Roof Sheets
In far North Queensland a recycling digester of natural vegetation decomposed matter so well that the caustic fumes coming from the material ate all that it encountered. The painted steel of the heavy earthmoving equipment used to move the vegetation corroded if left in the shed overnight. The roof of the building ultimately corroded away. The subcontractor was pursued by the contractor for this issue as well as non compliance with insurance under the contract. After a detailed review of the contract documents. Legal advice proposed to reject liability and resist the contractor’s claims. The matter settled without litigation after several months of heated negotiations.
top

Contract Drafting and general Contractual Advice

Deputised to the Standards Australia Drafting Committee
A secondment to the National Master Builders Association resulted in Brett Vincent’s deputisation as a drafter with the Standards Australia Drafting Committees. Representing builders in this instance, he presented arguments in relation to the formation of AS4000 and certain subcontracts in the Australian Standard suites. Successful arguments were raised to counter other industry lobby groups.

Shopping Centre in Western Sydney
Our people are currently involved in the drafting of a construction contract in Western Sydney. The $30 million development incorporates a lead retail tenant and a number of high profile secondary tenants. Our client has taken advantage of our lump sum offer for contract services and they have also received the benefit of our low hourly rates on other issues.

Consultants’ Contract Review
We represent two of the largest design companies in respect of the review of consulting contracts. We provide a detailed review of each of their consulting contracts from a common sense perspective. We review the contract, talk to the necessary people and consider the implications of the scope of works. We frequently identify examples of builders passing risk to the consultant when this cannot be properly covered by insurance.

Contractual Advice
Our client, a subcontractor, working on behalf of a main contractor was instructed to complete works by way of a separate oral order. The main contractor did not have proper contractual documentation. After the works of the subcontractor were no longer necessary, the contractor purported to create a written variation different from the original instruction. It was in short an attempt to defraud the subcontractor of his entitlement to payment. We were able to advise the subcontractor as to its rights and successfully recover the monies due to the subcontractor.

Overseas Contracts
Recently we have provided advice on an English contract for an engineering company concerning water treatment works in the United Arab Emirates. We did not recommend major changes to the contract but rather advised on the risks and what management changes needed to be made to counter those risks.

We continue to advise clients setting up offices in the region.
top

Building and Construction Industry Security of Payments Act

We have experience of running high profile cases in the Supreme Court in relation to injunctions to adjudications made under the Building and Construction Industry Security of Payments Act.

In Quasar v Demtech the demolisher, Demtech, failed to complete works. The contract was terminated and Demtech made a claim for loss of profit. Quasar, the builder, successfully defended the adjudication determination that was made in Demtech’s favour with our help.

In Co-ordinated Constructions v Hargreaves & Climatech, at first instance, Hargreaves & Climatech were successful in adjudication concerning the non-payment of services performed by it on a project in Kings Cross. The builder injuncted and ultimately was defeated.

Click here to review our simple diagram explaining the Security of Payments Act.
top

Insurance & Collapses

Bridge Collapse, Papua New Guinea
A claim was made concerning the collapse of a bridge in Papua New Guinea which was a result of the specialist sub consultant engineer not checking its design works. The main consulting engineer also did not check the works. The bridge was subject to extraordinary flood forces imposed during the wet season and earthquakes. The beam collapsed. The parties settled the issue of liability after a hard fought legal struggle. Brett Vincent was able to convince the negligent engineer to accept greater responsibility.

Coal Conveyor Collapse
A coal conveyor collapsed as a consequence of the cooling overnight of a poured slab on the conveying arm. The arm of the conveyor twisted and collapsed and fell onto the next conveyor. The next day workers walked onto the slab and felt it was peculiarly low. They very quickly departed. Upon discovering the collapse the engineers later stated over 1 km of conveyors could easily have fallen like a pack of cards. The liability under the insurance contract was very easily recognized and upon legal advice the insurer paid the builder to rectify the damage.
top

energy

State Electricity Reform Unit
The sale of electricity generation infrastructure for both dams and coal burning stations required the provision of due diligence reports on maintenance contracts. Brett Vincent provided the owners with advice on the liabilities under the maintenance contracts and provide a practical understanding of the potential problems concerning maintenance and payments in the future which would affect closure times, machinery life and electricity output.

Contractual Advice on High Voltage Line and Pylons
Two of the major contractors in this field regularly obtain advice from us. Recently we provided advice that required the reorganisation of our client’s claim to the principal. Importantly our advice resulted in pressure being placed on the Superintendent to reconsider the merits of our client’s argument. The pressure worked and the Superintendent recommended the Principal reconsider its position. Later negotiations settled the matter and resulted in additional payments for variation work to our client.
top

Railways

Voice Announcement System
A major electronic service provider was involved in an interesting case concerning a novel system of train identification and announcements at railway stations. Investigation of the contract was undertaken in relation to the use of existing wiring in the trains. It ultimately turned out that the wiring could not effectively transmit the necessary information without interference. It was a fundamental concept of the system that the existing wiring be used. With the legal advice the client understood its potential liability and was forearmed to reach a suitable settlement with the train owners.

Cracking Train Parts
Cracking of train parts on certain train types is not uncommon. Our role was the organisation and preparation of this matter, which took over a year and involved extensive expert analysis and the provision of contractual and litigation advice. This involved a substantial sum of money in relation to damages. Legal advice on the liability of the manufacture part and use was a critical issue. The case was successfully resolved for a positive outcome for the client. And yes the problem on the trains was corrected.
top

Airports

Baggage Handling Contract
The baggage handling contract at Sydney Airport involved the negotiation of not only equipment but a complex mathematical algorithm in relation to the bag distribution and sorting. An incredibly complex method is used to mechanically move bags from check in through to the relevant gate for loading onto a plane. Brett Vincent’s role, with the assistance of others, was to represent Sydney Airport against the contractor and supplier. The negotiation of this contract predominantly dealt with the purchase of a series of mathematical computations;. Everyone’s fear at the time was that the baggage handling system would fail as it had in Hong Kong. Accordingly there were additional warranties and requirements necessary for the contract to be drafted and executed. Not surprisingly there are special anti-terrorist features that needed to be considered in the contract as well. That is a secret though.

Mobile Stair Contracts, Airport Contaminated Waste Contracts, Telecommunications Contracts
Next time you board a plane, consider the countless number of contractors involved in the organisation of airport traffic, passengers and planes. The mobile stair contracts, waste disposal and telecommunications systems all run as a consequence of complicated agreements between players on and off the airport. One of the most unique is the runway de-rubbering which takes place late at night so that the planes do not slip on landing. Drafting or negotiating all of these types of contracts concerning the airport and its precinct requires an understanding of this technical environment.
top

Ports

Brett Vincent provided detailed advice to a Superintendent on variation and other contractual issues concerning a major port development work in Queensland. An interesting matter included the provision of detailed advice in respect of the sea bed batter design next to the wharves and contractual representations in tender documentation. We were able to review the drawings and specifications and find the correct answers for the client without further cost. An interesting piece of trivia – did you know that the buffers fixed to the side of the wharves are known as dolphins?
top

defence

Contractual Advice Concerning Diesel Engines.
The silent running of diesel engines is an important factor in military machinery. Accordingly it was an issue of considerable concern, amongst other issues in relation to the legal advice for the negotiating team. The negotiating team was able to successfully resolve a stalemate concerning the running of the engines, and the supply of parts and payments.

Low Frequency Telecommunications Maintenance Contracts. It is no secret that submarines throughout the world use very low frequency radio waves to communicate with the mainland while they are offshore. It makes for interesting maintenance contracts as personnel can only spend limited amounts of time within the area of the low frequency antennas before of the radio signals begin to cook them. The clearer drafting of maintenance contracts and provision of practical contractual advice in relation to the servicing of the antennas saw the owners of this unique equipment obtain better services from their suppliers.

Legislation/Government

Exemptions under the New South Wales Retail Leases Act, 1996 for Sydney Airport
As part of the upgrade of Sydney Airport for the Sydney Olympics, Brett Vincent was involved in obtaining exemptions to the New South Wales Retail Leases Act, 1986. It was necessary to obtain certain exemptions concerning the rapid movement of shops within the airport precinct at short notice for fit out and renovations. The exemptions under the Act were provided, after considerable lobbying with the State Government.

Draft Legislation for the Jakarta Docklands Development Authority, Indonesia
The Jakarta Docklands Development Authority required legislation to develop the foreshore of Jakarta in Indonesia. The development ultimately did not take place, however the proposal was for the massive reconstruction of the docklands area and reflected legislation from around the world. The core of the new Indonesian legislation was from New South Wales as used by the Darling Harbour Authority.
top